The National Assembly has passed the amended Law on Bidding, with 487 out of 489 participating delegates voting in favour, equivalent to 97.6%. The Law will take effect on 1 March 2027, except for the cases specified in Clause 4, Article 35. The amendments focus on tightening the conditions for direct contractor appointment, refining contractual provisions, and enhancing transparency in the determination of tender package prices. These changes will affect not only contractor selection procedures but also impose new requirements on cost management, legal compliance, and project scheduling across investment, construction, and infrastructure projects.
Table of Contents
1. Enhancing Transparency in Bidding Activities
The amended Law on Bidding was passed by the National Assembly on 21 November 2026 and comprises 8 chapters and 59 articles. Its primary objectives are to strengthen competition, transparency, and accountability in the selection of contractors and investors, while ensuring consistency between the Law on Bidding and sector-specific legislation.
Notably, the amendments focus on four key areas: tightening the conditions for direct contractor appointment; clarifying the scope of application of the Law on Bidding in relation to sector-specific legislation; refining provisions on contract execution and amendments; and strengthening the requirements governing the basis for determining tender package prices.
Previously, on 9 September 2026, the Government issued Decree No. 349/2026/ND-CP, amending and supplementing several provisions guiding the Law on Bidding in contractor selection. The Decree introduces a mechanism for publicly posting quotation requests on the National e-Procurement System, establishes minimum quotation submission periods, and encourages procuring entities to obtain multiple quotations to facilitate market price comparisons.
Overall, the ongoing refinement of the regulatory framework is aimed at strengthening controls across the bidding process, from tender package price determination and contractor selection to contract administration and performance monitoring.
2. Key Figures and Notable Regulatory Provisions
The following figures and regulatory requirements are worth noting:
Item | Information |
Percentage of delegates voting in favour | 97.6% |
Number of votes in favour | 487/489 |
Structure of the amended Law | 8 chapters, 59 articles |
Date of passage | 21 November 2026 |
General effective date | 1 March 2027 |
Date Decree No. 349 was issued | 9 September 2026 |
Minimum quotation submission period under ordinary circumstances | 3 working days |
Price deviation threshold subject to potential exclusion | More than 30% above or below the average price |
Under Decree No. 349/2026/ND-CP, procuring entities are required to publish quotation requests on the National e-Procurement System. At least one quotation must be obtained, while collecting more than one quotation is encouraged. Interested suppliers must submit their quotations within a period of no fewer than 3 working days from the date the request is published.
Where more than one quotation is received, the procuring entity may use the average price as a basis for determining the tender package price. In calculating the average, quotations or individual items within quotations whose prices are more than 30% higher or lower than the average may be excluded at the procuring entity's discretion, after which the average price may be recalculated.
For procurement packages involving medicines; chemicals, testing materials, and medical equipment; as well as components, accessories, and replacement materials used in medical equipment, the minimum quotation submission period is 10 days. Where two or more quotations are received, the procuring entity may select the highest quotation, provided it is consistent with its financial capacity and professional requirements.
Over the longer term, the Government has indicated its intention to further refine the rules governing tender package price determination, with a view to narrowing the circumstances in which a single quotation may be used and encouraging comparisons against average market prices and awarded prices for similar goods and services. These policy directions should be monitored as further implementing regulations are issued.

3. Key Changes Affecting Investment and Construction Activities
3.1. Tighter controls on direct contractor appointment
The Law provides more stringent conditions, criteria, and limits for direct contractor appointment in cases involving urgent or emergency circumstances, national defence and security tasks, and the protection of state secrets. The use of this procurement method does not exempt procuring entities from their responsibility to justify the appropriateness of the contractor selection decision.
3.2. Greater transparency in tender package pricing
Publicly disclosing quotation requests and encouraging the collection of quotations from multiple sources improve the ability to benchmark prices against market conditions and reduce the risk of unsupported price determination. However, average prices cannot replace an assessment of comparability in terms of technical specifications, quality standards, and supply conditions.
3.3. Greater flexibility in subcontractor engagement
The Law does not prescribe a fixed ratio or scope of work that must be assigned to subcontractors, allowing greater flexibility in organising specialised work packages such as mechanical, electrical and plumbing (MEP) systems, foundation works, fire prevention and firefighting systems, and landscaping. However, the engagement or replacement of subcontractors must still comply with the bidding documents, bid submissions, contractual provisions, and other applicable requirements. The main contractor remains responsible for the quantities, quality, schedule, and other obligations relating to work performed by subcontractors.
3.4. Stronger controls over contract amendments
Contract execution and amendments must be consistent with the contractor selection documents, the contractor selection results, and the agreements already signed. Any adjustments to the scope of work, quantities, contract price, or schedule must comply with applicable legal requirements and must not distort the outcome of the contractor selection process. Accordingly, the contractual framework and potential adjustment mechanisms should be carefully prepared from the bidding document preparation and contract negotiation stages.
4. Implications for Project Developers
For project developers involved in public-private partnership (PPP) projects, projects involving land use, infrastructure developments, or other projects with procurement packages falling within the scope of the bidding legislation, these changes introduce higher requirements for project preparation and implementation.
4.1. Legal compliance
Companies need to clearly distinguish between investor selection procedures and contractor selection procedures. They must also determine the applicable scope of the Law on Bidding and relevant sector-specific legislation for each component of a project. Establishing a legal compliance matrix and clearly defining the relevant authorities, responsibilities, and procedural requirements can help minimise the risk of document revisions or repeated administrative procedures.
4.2. Costs and total investment capital
Companies should develop cost databases covering construction materials, equipment, consultancy services, and construction works by work category. Quotations should be assessed against technical specifications, country of origin, project scale, and implementation conditions, rather than simply selecting the lowest quoted price.
4.3. Project schedules
Collecting and comparing quotations may require additional time, particularly where multiple sources need to be surveyed, technical specifications require clarification, or market prices need to be updated. Procurement planning should therefore be integrated early into the design and investment preparation stages, rather than being postponed until all project documentation has been completed.
4.4. Contractor management
Greater flexibility in subcontractor engagement allows main contractors to organise work packages according to specialised capabilities. However, this also requires stronger coordination, technical interface management, and quality control throughout project execution.
4.5. Financial management
Procuring entities should account for potential price fluctuations between the time tender package prices are established and the actual implementation period. They should also carefully manage price adjustment provisions, payment schedules, and contractual obligations to mitigate cash flow risks.
5. Key Considerations for Project Developers
The policy changes give rise to four key considerations.
First, legal risks are no longer confined to contractor selection decisions. They also extend to contract performance, including adjustments to the scope of work and subcontractor management.
Second, cost data is becoming an increasingly important management asset. Companies with established databases covering material prices, equipment costs, construction unit rates, and contractors' performance records will be better positioned to prepare cost estimates and control investment capital.
Third, project preparation capabilities are becoming increasingly important. Design documentation, work quantities, cost estimates, and market data need to be developed in a coordinated manner to minimise adjustments during the bidding process.
Fourth, contractor selection should be evaluated based on the overall balance of cost, quality, and schedule, rather than solely on the initial bid price.
6. Reshaping Contractor Selection Practices in the Long Term
The amended Law on Bidding 2026 reflects a broader trend towards greater transparency and accountability in investment and construction activities. For project developers, it provides a basis for upgrading cost management systems, supplier databases, contract administration, and project schedule controls.
Over the long term, a company's competitive advantage will depend not only on its ability to secure land banks and access funding, but also on its capacity to organise project execution, control costs, and manage the entire investment lifecycle. Proactively adapting to the new regulatory framework will help mitigate legal risks, protect investment efficiency, and enhance project feasibility.